Build a reliable acceptance ledger for contact temperature monitoring using three layers — measuring points, communication and firmware version.
1. Layer one: fix the measuring points
Before any communication test, agree with the site engineer on the physical measuring points. For a withdrawable switchgear cubicle the usual set is: the two isolating contacts per phase, the cable terminations, and the busbar joint. Mark each point on the single-line diagram and give it an address that will never change, for example CB-03 / upper contact / phase L2. A monitoring system that produces temperatures without a stable address is not usable during an outage review.
- Confirm the sensor fixing method (bolt-on lug, busbar clamp or embedded probe) suits the conductor size.
- Record the ambient reference point separately — absolute temperature alone is difficult to judge.
- Photograph every installed point and attach the photo to the acceptance sheet.
2. Layer two: verify the communication path
With the measuring points fixed, verify that every reading actually reaches the supervision host. Poll the register map once at the panel and once at the gateway, and compare. Differences at this stage are almost always addressing or termination problems, not sensor problems.
- Check the bus topology: one daisy chain, not a star, with termination at the two physical ends only.
- Confirm baud rate and parity are identical on every device on the segment.
- Log a 24-hour soak test and record the number of dropped polls — it should be zero.
3. Layer three: record firmware and thresholds
The third layer is the one most often skipped. Record the firmware version of every sensor node and of the display unit, together with the alarm thresholds actually written into the device. Threshold sets drift over maintenance cycles; a signed record at handover is what makes later comparisons meaningful.
4. What to sign off
An acceptance file is complete when it contains: the annotated single-line diagram, the photo log, the poll comparison table, the 24-hour soak result, and the firmware/threshold register. Five documents, one folder — that is the whole ledger.